progress photos

A collection of photos from day one of construction

AF T Hangars, Dec 31, 2014

All Hangers, Dec 1

 

T-Hangar interior, dec 1

exec hangars interior, dec 1

All Hangars, Oct 11

AG Exec Hangars, Oct 11

All hangars, Sep 18

AG Hangars, Sep 3

AF & AG Hangars, Sep 3

AE Hangars, Sep 3

Aug 3rd, looking north, row ae

aug 3rd, looking north, row ae

AUG 1ST, ROW AE CONSTRUCTION

AUG 1ST, ROW A3 CONSTRUCTION

 

July 26, row AG's preparation for vertical construction

July 26, row AF's foundation progress

July 26, row AE's foundation progress

June 18, AE floor, lookinG North

June 18, AE Floor, Looking West

June 16, Midnight Pour of Row AE floor

 

June 7, 2014 (Looking West)

All the underground utilities and fire line have been installed. Stem walls on AE hangar building have been poured. The final slab is to be poured this next week, (June 9th through 13th). Metal is scheduled to be delivered the week of June 23rd.

 

May 30, 2014 (looking North)

may 17, 2014

 

May 9, 2014

 

May 1, 2014